A rapid tool is an injection mold made of soft steel, designed for small and medium production series. It lasts for tens of thousands of parts, is built in about half the time of a standard production mold, and costs tens of percent less. At GoldMold, first parts from a rapid tool arrive in about two weeks.
Production takes place in China, supervised by GoldMold's own engineers on site. Every project is personally managed by Emmanuel Goldschmidt, a Technion-trained mechanical engineer who has managed manufacturing in China since 1997.
Rapid tool vs. standard production mold
| Rapid tool | Standard production mold | |
|---|---|---|
| Mold material | Soft steel | To production requirements |
| Best for | Small and medium series, up to tens of thousands of parts | Large series |
| Time to first parts | About two weeks | Up to about four weeks for a complex mold |
| Cost | Tens of percent less | Higher |
Who it is for
- Startups moving from development to production that need real parts in the final material before investing in a production mold.
- Small and medium series, when a full production mold is not justified.
- Market tests and pilots before full-scale production.
What we mean by small and medium series
| Series | Units |
|---|---|
| Small | 10–100 |
| Medium | 100–500 |
| Large | 500 up to 1 million |
Silicone: compression molds for development
For silicone parts in development quantities, we make compression molds in a very short time. When a part must be flash-free, transparent or thin-walled, we move to LSR injection molding. See LSR silicone injection and compression molding.
The mistake to avoid
The most common mistake when moving to production is going to tooling before the design is 100% final, or with the wrong material. The result can be a delay of six months to a year, and in extreme cases an immature product reaching the market and damaging the whole project. That is why Emmanuel personally reviews the drawings before a mold is built, and recommends changes where needed.
Process
- Drawing review and design and material recommendations.
- Fast quotation.
- Mold build and first parts in about two weeks, usually with 1–3 correction rounds until approval.
- Series production.
- Delivery to the customer: express in about 4 days, regular air freight in 8–10 days, sea freight in 4–5 weeks. GoldMold handles all logistics.
FAQ
How many parts does a rapid tool last?
Tens of thousands of parts. It is made of soft steel.
How much time and money does it save compared with a standard mold?
About half the time, and tens of percent of the cost.
How long until first parts?
About two weeks from ordering the mold.
What happens when quantities grow?
We move to a production mold. Our advantage is that we scale quantities fast, from a small series up to a million units.
Contact us
Send your drawing or CAD file to Emmanuel Goldschmidt. He will review it personally and get back to you with comments and a quote.
Mobile: +972-54-4482065 · Office: +972-4-8110531 · Email: [email protected] · 22 Ha'ashlag St., Haifa, Israel